Timeline to Open

The ideal four months

From signed agreement to opening day, the ideal path is about four months. Build-out is the long pole at three to four months, and the rest happens alongside it. Design and permits are the one part nobody can promise: plan on at least a month, and know that municipal timing is what stretches it.

M1M2M3M4M5
  1. Discovery & qualification

    FDD review, discovery call, territory reservation

    1 wk
  2. Franchise agreement & financing

    Lender introduction, CSBFL application, agreement signed

    2 wks
  3. Site selection & lease

    Trade-area analysis, LOI, lease with rent-free build period

    3 wks
  4. Design & permits

    Pre-approved layout adapted to the unit, building permit. Permit timing depends on the municipality; no timeline can be guaranteed.

    1 month minimum
  5. Build-out

    Framing, electrical, low-voltage, bay enclosures, turf

    3–4 months
  6. Training

    Operator training during construction: platform, access control, maintenance, member support

    3 days
  7. Equipment & automation install

    TrackMan iO, projectors, access control, cameras, booking integration

    2 wks
  8. Soft launch & grand opening

    Test bookings, member pre-sales, launch campaign

    1 wk

4 months from signed agreement to grand opening. This is the ideal case. Build-out is 3–4 months. Design and permits need at least a month and are open-ended because permit timing depends on the municipality.

PhaseStarts (week)DurationWhat happens
Discovery & qualification01FDD review, discovery call, territory reservation
Franchise agreement & financing12Lender introduction, CSBFL application, agreement signed
Site selection & lease13Trade-area analysis, LOI, lease with rent-free build period
Design & permits21 month minimum (open-ended)Pre-approved layout adapted to the unit, building permit. Permit timing depends on the municipality; no timeline can be guaranteed.
Build-out63–4 monthsFraming, electrical, low-voltage, bay enclosures, turf
Training113 daysOperator training during construction: platform, access control, maintenance, member support
Equipment & automation install162TrackMan iO, projectors, access control, cameras, booking integration
Soft launch & grand opening181Test bookings, member pre-sales, launch campaign